HEIDRUN / MARINER 

Project: Mariner FSU Transportation and Mooring InstallationMariner

Position: Mobilisation manager

Project Description: Pre Installation of the new STL system consisting of a 12 legs mooring

system with pile anchors, bottom chain 158mm, wire segments with buoyancy elements

Location: UK sector of the North Sea, Water Depth 110m

Installation Vessel: Boa Sub C

Mobilisation Base: NorSea AS, Tananger 

 

Project: Heidrun FSU Transportation and Mooring Installation

Position: Mobilisation manager

Project Description: Removal and disposal of the existing loading system includingSTL buoy,

mooring lines with ancillaries and anchors

Pre Installation of the new STL system consisting of a 12 legs mooring system with suction anchors,

bottom chain 152mm, wire segments with buoyancy elements

Towing of the Heidrun FSU from South Korea/Samsung Heavy Industries

Location: North Sea, Water Depth 360m

Installation Vessel: Boa Sub C

Mobilisation Base: Vestbase

 

 